Recently completed
- BAS Controls Upgrade, AO
- HVAC Ventilation Upgrades (Bldgs D, T, A), Downtown
- HVAC Ventilation Upgrades (Towers 1, 2, 3, 4 & 6 AHUs), North
- BAS Controls Upgrade and VAV Replacement, Nassau
- HVAC Ventilation Upgrades (Bldg M1, W & G), South
Projects in progress
Ongoing Collegewide:
- Scan/Digitize Facilities Plans
- Master Plan, 5-Year Plant Survey
- Air & Ventilation Enhancement (CARES Act), Downtown, Kent, North and South
- Exterior Door Lock Conversion to Access Control System, Downtown, Kent and North
Cecil Center:
- Construction, San Jose Early College
Deerwood Center:
- Center Stage Elevator Modernization
- Nursing Expansion (Phase I & II)
Downtown Campus:
- Human Resources Renovation, AO
- 150-Ton Chiller Replacement, ATC
- Chillers, Pumps and Cooling Tower Replace (C Bldg)
- 20+ Year Re-roof, Multiple Bldgs
- Building Envelope Study (A, B, C & D Bldgs)
- Building Envelope Removal/Replace Curtain Wall, URC
Nassau Center:
- Commercial Vehicle Driving Grant
- Nursing Expansion (Phase I & II)
- Classroom Upgrades, Furniture
North Campus:
- Cardiovascular Tech, Remodel
- Parking Lots 1-4 and 6 Repave & JTA Bus Stop Relocation
- Restroom Upgrades (A Bldg)
South Campus:
- Chiller and Pump Replacement
- Veteran Support Center (U Bldg)
- Door Access Control Upgrade (D & T Bldgs)
- Cybersecurity Lab (B-107)
|
Projects in planning
Cecil Center:
- Gun Range Assessment
- Exterior Door Access Control Upgrade (Cecil-North & South)
Deerwood Center:
Downtown Campus:
- Follett Bookstore Renovation
Kent Campus:
- Pavement Repairs, Borings/Restripe
- Continue Door Access Control Upgrade (E, F & G Bldgs)
- Follett Bookstore Renovation
- Student Life (SGA) Meeting Room
Nassau Center:
- Exterior Door Access Control Upgrade (A/B & T Bldgs)
North Campus:
- Student Services Update
- Surgical Tech - 2nd Floor (A Bldg), Programming & Conceptual Design
- Tower 3, Restrooms
- Towers, Continue Nonslip Coating & Treads
- Ceiling Tiles, 3rd Floor (C Bldg)
- SIM Center Restrooms (E Bldg)
- Negative Pressure Correction (C & D Bldgs)
- Continue Door Access Control Upgrade (B, C, D, E & F Bldgs)
- Pavement Resurface (CJC Skills Pad & Track)
South Campus:
- Follett Bookstore Renovation
- Science Lab Negative Pressure Correction (E & F Bldgs)
- Replace existing duct board with metal duct (C & D Bldgs)
- Wilson Center Sculpture
- 20+ Year Re-roof, Multiple Bldgs
- Pavement Resurface (Skills Pad & EVOC Course
|
|
|
|