Recently completed
- Artist Series Refresh, AO
- Ventilation Upgrade, Kent
- Elevator Modernization, North
- Tower Leak Repairs, Cecil
Projects in progress Ongoing Collegewide:
- Scan/Digitize Facilities Plans
- Master Plan, 5-Year Plant Survey
- Air & Ventilation Enhancement (CARES Act), Downtown, Kent, North and South
- Exterior Door Lock Conversion to Access Control System, Downtown, Kent and North
Cecil Center:
- Construction, San Jose Early College
Deerwood Center:
- Center Stage Elevator Modernization
- Marquee Sign, Neon Lighting
- Nursing Expansion (Phase I & II)
Downtown Campus:
- Human Resources Renovation, AO
- BAS Controls Upgrade, AO
- 150-Ton Chiller Replacement, ATC
- Chillers, Pumps and Cooling Tower Replace (C Bldg)
Nassau Center:
- Commercial Vehicle Driving Grant
- BAS Controls Upgrade and VAV Replacement
- Nursing Expansion (Phase I & II)
North Campus:
- Cardiovascular Tech, Remodel
- Parking Lots 1-4 and 6 Repave & JTA Bus Stop Relocation
- Restroom Upgrades (A Bldg)
South Campus:
- Chiller and Pump Replacement
- Veteran Support Center (U Bldg)
- Door Access Control Upgrade (D & T Bldgs)
- Cybersecurity Lab (B-107)
|
Projects in planning Cecil Center:
- Gun Range Assessment
- Exterior Door Access Control Upgrade (Cecil, North & South)
Deerwood Center:
Downtown Campus:
- Follett Bookstore Renovation
Kent Campus:
- Pavement Repairs - Borings/Restripe
- Continue Door Access Control Upgrade (E, F & G Bldgs)
- Follett Bookstore Renovation
- Student Life (SGA) Meeting Room
Nassau Center:
- Exterior Door Access Control Upgrade (A/B & T Bldgs)
- Classroom Renovations
North Campus:
- Student Services Update
- Surgical Tech - 2nd Floor (A Bldg) – Programming & Conceptual Design
- Tower 3, Restrooms
- Towers, Continue Nonslip Coating & Treads
- Replace Ceiling Tiles, 3rd Floor (C Bldg)
- SIM Center Restrooms (E Bldg)
- Negative Pressure Correction (C & D Bldgs)
- Continue Door Access Control Upgrade (B, C, D, E & F Bldgs)
South Campus:
- Follett Bookstore Renovation
- Science Lab Negative Pressure Correction (E & F Bldgs)
- Replace existing duct board with metal duct (C & D Bldgs)
- Wilson Center Sculpture
|
|
|
|